Corpus Christi Liquefaction

Corpus Christi Liquefaction

Customer Name: Bechtel | Corpus Christi Liquefaction, LLC

Project Location: San Patricio County, TX

Project Summary
Corpus Christi Liquefaction, LLC (Corpus Christi Liquefaction), a subsidiary of Cheniere Energy, is developing and constructing a liquefied natural gas (LNG) export terminal at one of Cheniere’s existing sites that was previously permitted for a regasification terminal. The liquefaction project is being designed for three trains with expected aggregate nominal production capacity of up to 13.5 million tonnes per annum (mtpa) of LNG. Up to seven midscale liquefaction trains adjacent to the CCL Project (“Corpus Christi Stage 3”) are also being developed. The total expected nominal production capacity of the seven midscale trains is approximately 9.5 mtpa of LNG.
The Corpus Christi site is located on the La Quinta Channel on the northeast side of Corpus Christi Bay in San Patricio County, Texas, on over 1,000 acres owned or controlled by Cheniere and is approximately 15 nautical miles from the coast.

Scope of Work
GSS was contracted by Bechtel to provide front end Scaffolding Design, Estimating and Asset Management Services for the Corpus Christi project.

Impact
GSS successfully supported CCL with over 18,000 scaffold requests and in excess of 2.25 million man hours; and over 6,500t of scaffold material. 
Share by: